Title: Work Breakdown Structure- Case Study Answer
Description: This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc. https://doi.org/10.1002/9780470549179
Description: This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc. https://doi.org/10.1002/9780470549179
Document Preview
Extracts from the notes are below, to see the PDF you'll receive please use the links above
CASE STUDIES IN PROJECT MANAGEMENT SYSTEMS
Work Breakdown Structure as a Skeleton for Integration
Wilson Clark and Dragan Z
...
PROBLEM AND SOLUTION
Problem: The WBS created was inefficient since it overlapped with the other commitments of the
engineers
...
I
...
This was due to the inability of
the project manager of Lada to consider the other priorities of the engineers from the OptoMechanical Group
...
Also, it was raised in the meeting about the possibility that the project manager was trying
to micromanage the Opto-Mechanical Group since the project manager interfered with their
activities on deliverables
...
Whereas it would be validated with major parties of the project to avoid concerns like overlapping
with projects with higher priorities
...
BRIEF HISTORY
Matt Boon is the engineering manager of the Opto - Mechanical Group, while Percy Bedge
is the project manager of Lada
...
During their conversation, they didn’t show much cooperation
which lead to an atmosphere of conflict and pressure between them
...
Also, Percy scheduled them in a certain period
that overlapped with many prioritized projects
...
Moreover, he raised the issue regarding the ownership issue which he thought was
concluded already
...
Nevertheless, Matt voiced out to Percy that it looked like he was trying to micromanage them
again since Percy ignored the Project Manager’s charter of the company
...
Micromanagement generally has a negative connotation since
this results in (1) Loss of control; (2) Loss of trust; (3) Dependent employees; (4) Your burnout;
(5) High turnover of staff; (6) Lack of autonomy
...
ALTERNATIVES
Option #1: Create a Statement of Work (SOW)
...
It covers
the working agreement between two parties: the client, buyer, or government entity, and
the agency, vendor, or contractor
...
Having a solid understanding of the scope of the project helps all parties involved
avoid scope creep
...
Provide information on performance outcomes as well as standards and metrics
...
Complexity
2
...
Time commitment
4
...
Scope of work describes the specific tasks the contractor will perform to meet
objectives
...
Pros:
1
...
2
...
Cons:
1
...
Time commitment
Option #3: Create an efficient WBS and proceed with other project requirements
...
Like in case, they should consider the priorities or other
commitments of the engineers from Opto - Mechanical Group
...
Boosts productivity
2
...
Boosts transparency and accountability
4
...
Identifies risk in a better way
6
...
Having a step-by-step approach is a pain!
2
...
No Buying in processes were used
4
...
The orientation
6
...
Can’t get you correct details
8
...
Create a Statement of
Work (SOW)
2
...
Create an efficient
WBS and proceed
with other project
requirements
...
EFFICIENCY
(TIME)
ECONOMY
(COST)
EFFECTIVITY
TOTAL
3
1
2
6
1
2
1
4
2
3
3
8
RECOMMENDATION
I recommend Option #3 which is to create an efficient WBS and proceed with other project
requirements as a solution to the problem regarding the inefficient WBS that was first created since
it overlapped with the other commitments of the engineers
...
IMPLEMENTATION
CREATE AN EFFICIENT WBS AND PROCEED WITH OTHER PROJECT
REQUIREMENTS
...
Level
of Effort
Lead
Person
PLANNING
Plan and
Supervise
Requirements
All task management and
management activities
Roll-up
Task
N/A
Project
Manager
Create Plan
WBS,
40 hrs
Project
Manager
Development of WBS, work
package identification,
schedule formulation, staffing
projection, resource estimation
...
WBS
Dictionary,
MS Project
Plan
Create Budget
PR
40 hrs
Project
Manager
Development and
documentation of the project
budget based on plan and
resources
Prepare
Disbursement /
Reconciliation
Purchase
Orders,
Deliverable
Product
Acceptance
Form
40 hrs
CFO
Development of disbursement
process for the project
including acceptance/approval
forms
...
pluralsight
...
smartsheet
Title: Work Breakdown Structure- Case Study Answer
Description: This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc. https://doi.org/10.1002/9780470549179
Description: This note includes my personal answer to cases in the book mentioned below: Milosevic, D. Z., Patanakul, P., & Srivannaboon, S. (2010). Case Studies in Project, Program, and Organizational Project Management. John Wiley and Sons Inc. https://doi.org/10.1002/9780470549179