Search for notes by fellow students, in your own course and all over the country.

Browse our notes for titles which look like what you need, you can preview any of the notes via a sample of the contents. After you're happy these are the notes you're after simply pop them into your shopping cart.

My Basket

You have nothing in your shopping cart yet.

Title: Chapter 13 Notes - Monitoring Progress
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550

Document Preview

Extracts from the notes are below, to see the PDF you'll receive please use the links above


FA - Chapter 13

BUSI 2550

11/12/2018

Progress and Performance Measurement and Evaluation

Structure of Project Monitoring Information System







Involves determining what data to collect, how, when and who will collect, analysis and
reporting of data
Step 1: determine what data is collected
o Data collected are determined by which metrics used for project control
o Typical key data collected: actual activity duration times, resource usage/rates, actual
costs vs
...
?
o Reporting period 1 hr, 1 day, 1 week?
o Central repository for data and who is responsible for dissemination?
Step 3: Reports and Reporting
o Design report for appropriate audience
...
planned performance to identify deviations, evaluate alternatives
and take corrective action
Project control steps for measuring and evaluating performance:
o 1 – Setting Baseline Plan
 Provides elements for measuring performance
 Derived from WBS and network/resource scheduling decisions
o 2 – Measuring Progress and Performance
 Quantitative measures: time and budget
 Qualitative measures: meeting customer tech
...
expected plans
 More frequent status reports allow for early detection of causes of variations
4 – Taking Action
 Scope can sometimes change leading to baseline plan changing as well

Monitoring Time Performance








11/12/2018

Goal of progress reporting is to catch negative variances from
plan early
Gantt charts, control charts and milestone schedules are used as
project schedule status’s
Tracking Gantt Chart – Compares planned vs
...
2012–January 15, 2013

1% For Art Selection:

November 2012–May 31, 2013

Bid and Permit:

January–March 31, 2013

Construction:

April 2013–August 31, 2014

Furnishing Selections:

September–November 30, 2013

Occupancy:

September 7, 2014

2

FA - Chapter 13

BUSI 2550

11/12/2018

Development of Earned Value Cost/Schedule System



Planned budgeted value (PV) – project budget baseline
Earned Value provides missing links not found in cost-budget systems (can be used to create
status reports)

EV

Earned value for a task is percent complete times original budget
...
An approved cost
estimate of the resources scheduled in a time-phased cumulative baseline

AC

Actual cost of the work completed
...
CV = EV − AC
...

SV = EV − PV
...
The total budgeted cost of the baseline or project cost
accounts
...


ETC

Estimated cost to complete remaining work
...
VAC indicates expected actual over- or underrun cost at
completion
...
Develop following documents:
 Scope
 Work packages
 Deliverables
 Organization Units
 Resources
 Budgets for work packages
o 2 - Develop work/resource schedule
 Schedule resources to activities
 Time-phase work packages into a network
o 3 - Develop time-phase budgets using work packages
 Cumulative value of budgeted value for work packages becomes baseline/PV
o 4 - Collect actual costs for work performed (at work package level)
 Called AC (actual cost) of work completed
 Collect percent complete and multiply it with original budget to get earned
value
o 5 – Compute Schedule Variance and Cost Variance
 Schedule variance = EV-PV
 Cost Variance = EV-AC
 Prepare status reports for each level of management

3

FA - Chapter 13












BUSI 2550

11/12/2018

 Actual time performance compared to project network schedule
Baseline is created to monitor/report progress and estimate cash flow
Percent Complete Rule – rule of any earned value system
o Best method is to establish frequent checkpoints over duration of work packages and
assign completion percentages in $’s
Baseline (PV) is sum of cost accounts
o Each cost account is sum of work packages in cost
account
o 3 direct costs that PM’s can control included:
labor, equipment and materials
2 key computation for measuring accomplishments
o 1 – Compare EV with expected schedule value
o 2 – Compare EV with AC
3 data elements to assess status using EV (used to
compute SV and CV)
o 1 – PV – planned cost of work scheduled
o 2 – EV – budgeted cost of work completed
o 3 – AC – Actual cost of work completed
Cost Variance – identifies if work accomplished costs
more/less than was planned
o negative SV/CV = problem or changes that have
taken place
o Schedule Variance – measures progress in dollars
rather than time units
 Does NOT contain CP info
...
Baseline Development
a
...
Baseline Gantt Chart

c
...
Development of Status Report
a
...
Work packages are in one of these conditions: not started, finished, in-process
Status Report: Ending Period 1
Task

%Complete

EV

AC

PV

CV

SV

50%

10

10

10

0

0

10

10

10

0

0

%Complete

EV

AC

PV

CV

SV

Finished

20

30

20

−10

0

20

30

20

−10

0

%Complete

EV

AC

PV

CV

SV

A

Finished

20

30

20

−10

0

B

33%

5

10

5

−5

0

C

20%

20

30

20

−10

0

D

60%

21

20

15

+1

+6

66

90

60

−24

+6

EV

AC

PV

CV

SV

A
Cumulative Totals
Status Report: Ending Period 2
Task
A
Cumulative Totals
Status Report: Ending Period 3
Task

Cumulative Totals
Status Report: Ending Period 4
Task

%Complete

5

FA - Chapter 13

BUSI 2550

11/12/2018

A

Finished

20

30

20

−10

0

B

Finished

15

20

15

−5

0

C

50%

50

70

50

−20

0

D

80%

28

30

25

−2

+3

113

150

110

−37

+3

%Complete

EV

AC

PV

CV

SV

A

Finished

20

30

20

−10

0

B

Finished

15

20

15

−5

0

C

60%

60

100

80

−40

−20

D

80%

28

50

35

−22

−7

123

200

150

−77

−27

%Complete

EV

AC

PV

CV

SV

A

Finished

20

30

20

−10

0

B

Finished

15

20

15

−5

0

C

80%

80

110

100

−30

−20

D

Finished

35

60

35

−25

0

150

220

170

−70

−20

%Complete

EV

AC

PV

CV

SV

A

Finished

20

30

20

−10

0

B

Finished

15

20

15

−5

0

C

90%

90

120

100

−30

−10

D

Finished

35

60

35

−25

0

E

0%

0

0

30

0

−30

F

0%

0

0

0

0

0

160

230

200

−70

−40

Comulative Totals
Status Report: Ending Period 5
Task

Cumulative Totals
Status Report: Ending Period 6
Task

Cumulative Totals
Status Report: Ending Period 7
Task

Cumulative Totals

b
...
Gantt Chart showing status

d
...
00 = progress is as planned

7

11/12/2018

FA - Chapter 13









BUSI 2550

11/12/2018

Index of 1
...
00 Under cost Ahead of schedule
o Cost Efficiency
 CPI = EV/AC
=1
...
7 (for every $0
...
00 Over cost
Behind schedule
work planned is completed for every $1
actually spend)
o Scheduling Efficiency
 SPI = EV/PV
 SPI = 160/200 = 0
...
8 of work has been completed for
every $1 worth of scheduled work)
Two indexes for Project Percent Complete
o Compare the current progress to end of project
o Percent Complete Index Budgeted costs
 PCI) = EV / BAC
 PCIB = 160/320 = 0
...
40 = 40%
 Managers favor this index as it contains actual/revised estimates
o Third index used in construction industry: Management Reserve Index
 MRI = CV / MR
0/100 rule – assumes credit is fully earned for work completed
...

50/50 rule – 50 percent of value of work package to be earned once started and 50 percent to
be earned when completed
Percent complete with weighted monitoring gates – uses subjective estimated percent complete
in combination with hard, tangible monitoring points
...

o Frequently used to authorize progress payments to contractors

Forecasting Final Project Cost


2 Methods to revise estimates of future project costs:
o Revised Estimated Cost at Completion (EACre)
 EACre = AC + ETCre
 Revised estimated cost at completion = cumulative actual cost of work
completed + revised estimated cost to complete remaining work
o Forecasting model (EACf)
 EACf = ETC + AC
 ETC = Work Remaining / CPI = (BAC – EV) / (EV / AC)
 Forecasted total cost of completion (EACf) = Estimated total cost to complete
remaining work (ETC) + Cumulative actual cost of work completed (AC)

8

FA - Chapter 13


BUSI 2550

To Complete Performance Index (TCPI) – measures amount of value each remaining dollar in
budget must earn to stay on budget
o TCPI = (BAC – EV) / (BAC – AC)

Other Control Issues


11/12/2018

Issues in maintaining control of projects
o Technical performance measurement
o Scope creep
o Baseline changes
o Data acquisition costs and problems

9


Title: Chapter 13 Notes - Monitoring Progress
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550