Search for notes by fellow students, in your own course and all over the country.
Browse our notes for titles which look like what you need, you can preview any of the notes via a sample of the contents. After you're happy these are the notes you're after simply pop them into your shopping cart.
Title: Chapter 13 Notes - Monitoring Progress
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550
Document Preview
Extracts from the notes are below, to see the PDF you'll receive please use the links above
FA - Chapter 13
BUSI 2550
11/12/2018
Progress and Performance Measurement and Evaluation
Structure of Project Monitoring Information System
Involves determining what data to collect, how, when and who will collect, analysis and
reporting of data
Step 1: determine what data is collected
o Data collected are determined by which metrics used for project control
o Typical key data collected: actual activity duration times, resource usage/rates, actual
costs vs
...
?
o Reporting period 1 hr, 1 day, 1 week?
o Central repository for data and who is responsible for dissemination?
Step 3: Reports and Reporting
o Design report for appropriate audience
...
planned performance to identify deviations, evaluate alternatives
and take corrective action
Project control steps for measuring and evaluating performance:
o 1 – Setting Baseline Plan
Provides elements for measuring performance
Derived from WBS and network/resource scheduling decisions
o 2 – Measuring Progress and Performance
Quantitative measures: time and budget
Qualitative measures: meeting customer tech
...
expected plans
More frequent status reports allow for early detection of causes of variations
4 – Taking Action
Scope can sometimes change leading to baseline plan changing as well
Monitoring Time Performance
11/12/2018
Goal of progress reporting is to catch negative variances from
plan early
Gantt charts, control charts and milestone schedules are used as
project schedule status’s
Tracking Gantt Chart – Compares planned vs
...
2012–January 15, 2013
1% For Art Selection:
November 2012–May 31, 2013
Bid and Permit:
January–March 31, 2013
Construction:
April 2013–August 31, 2014
Furnishing Selections:
September–November 30, 2013
Occupancy:
September 7, 2014
2
FA - Chapter 13
BUSI 2550
11/12/2018
Development of Earned Value Cost/Schedule System
Planned budgeted value (PV) – project budget baseline
Earned Value provides missing links not found in cost-budget systems (can be used to create
status reports)
EV
Earned value for a task is percent complete times original budget
...
An approved cost
estimate of the resources scheduled in a time-phased cumulative baseline
AC
Actual cost of the work completed
...
CV = EV − AC
...
SV = EV − PV
...
The total budgeted cost of the baseline or project cost
accounts
...
ETC
Estimated cost to complete remaining work
...
VAC indicates expected actual over- or underrun cost at
completion
...
Develop following documents:
Scope
Work packages
Deliverables
Organization Units
Resources
Budgets for work packages
o 2 - Develop work/resource schedule
Schedule resources to activities
Time-phase work packages into a network
o 3 - Develop time-phase budgets using work packages
Cumulative value of budgeted value for work packages becomes baseline/PV
o 4 - Collect actual costs for work performed (at work package level)
Called AC (actual cost) of work completed
Collect percent complete and multiply it with original budget to get earned
value
o 5 – Compute Schedule Variance and Cost Variance
Schedule variance = EV-PV
Cost Variance = EV-AC
Prepare status reports for each level of management
3
FA - Chapter 13
BUSI 2550
11/12/2018
Actual time performance compared to project network schedule
Baseline is created to monitor/report progress and estimate cash flow
Percent Complete Rule – rule of any earned value system
o Best method is to establish frequent checkpoints over duration of work packages and
assign completion percentages in $’s
Baseline (PV) is sum of cost accounts
o Each cost account is sum of work packages in cost
account
o 3 direct costs that PM’s can control included:
labor, equipment and materials
2 key computation for measuring accomplishments
o 1 – Compare EV with expected schedule value
o 2 – Compare EV with AC
3 data elements to assess status using EV (used to
compute SV and CV)
o 1 – PV – planned cost of work scheduled
o 2 – EV – budgeted cost of work completed
o 3 – AC – Actual cost of work completed
Cost Variance – identifies if work accomplished costs
more/less than was planned
o negative SV/CV = problem or changes that have
taken place
o Schedule Variance – measures progress in dollars
rather than time units
Does NOT contain CP info
...
Baseline Development
a
...
Baseline Gantt Chart
c
...
Development of Status Report
a
...
Work packages are in one of these conditions: not started, finished, in-process
Status Report: Ending Period 1
Task
%Complete
EV
AC
PV
CV
SV
50%
10
10
10
0
0
10
10
10
0
0
%Complete
EV
AC
PV
CV
SV
Finished
20
30
20
−10
0
20
30
20
−10
0
%Complete
EV
AC
PV
CV
SV
A
Finished
20
30
20
−10
0
B
33%
5
10
5
−5
0
C
20%
20
30
20
−10
0
D
60%
21
20
15
+1
+6
66
90
60
−24
+6
EV
AC
PV
CV
SV
A
Cumulative Totals
Status Report: Ending Period 2
Task
A
Cumulative Totals
Status Report: Ending Period 3
Task
Cumulative Totals
Status Report: Ending Period 4
Task
%Complete
5
FA - Chapter 13
BUSI 2550
11/12/2018
A
Finished
20
30
20
−10
0
B
Finished
15
20
15
−5
0
C
50%
50
70
50
−20
0
D
80%
28
30
25
−2
+3
113
150
110
−37
+3
%Complete
EV
AC
PV
CV
SV
A
Finished
20
30
20
−10
0
B
Finished
15
20
15
−5
0
C
60%
60
100
80
−40
−20
D
80%
28
50
35
−22
−7
123
200
150
−77
−27
%Complete
EV
AC
PV
CV
SV
A
Finished
20
30
20
−10
0
B
Finished
15
20
15
−5
0
C
80%
80
110
100
−30
−20
D
Finished
35
60
35
−25
0
150
220
170
−70
−20
%Complete
EV
AC
PV
CV
SV
A
Finished
20
30
20
−10
0
B
Finished
15
20
15
−5
0
C
90%
90
120
100
−30
−10
D
Finished
35
60
35
−25
0
E
0%
0
0
30
0
−30
F
0%
0
0
0
0
0
160
230
200
−70
−40
Comulative Totals
Status Report: Ending Period 5
Task
Cumulative Totals
Status Report: Ending Period 6
Task
Cumulative Totals
Status Report: Ending Period 7
Task
Cumulative Totals
b
...
Gantt Chart showing status
d
...
00 = progress is as planned
7
11/12/2018
FA - Chapter 13
BUSI 2550
11/12/2018
Index of 1
...
00 Under cost Ahead of schedule
o Cost Efficiency
CPI = EV/AC
=1
...
7 (for every $0
...
00 Over cost
Behind schedule
work planned is completed for every $1
actually spend)
o Scheduling Efficiency
SPI = EV/PV
SPI = 160/200 = 0
...
8 of work has been completed for
every $1 worth of scheduled work)
Two indexes for Project Percent Complete
o Compare the current progress to end of project
o Percent Complete Index Budgeted costs
PCI) = EV / BAC
PCIB = 160/320 = 0
...
40 = 40%
Managers favor this index as it contains actual/revised estimates
o Third index used in construction industry: Management Reserve Index
MRI = CV / MR
0/100 rule – assumes credit is fully earned for work completed
...
50/50 rule – 50 percent of value of work package to be earned once started and 50 percent to
be earned when completed
Percent complete with weighted monitoring gates – uses subjective estimated percent complete
in combination with hard, tangible monitoring points
...
o Frequently used to authorize progress payments to contractors
Forecasting Final Project Cost
2 Methods to revise estimates of future project costs:
o Revised Estimated Cost at Completion (EACre)
EACre = AC + ETCre
Revised estimated cost at completion = cumulative actual cost of work
completed + revised estimated cost to complete remaining work
o Forecasting model (EACf)
EACf = ETC + AC
ETC = Work Remaining / CPI = (BAC – EV) / (EV / AC)
Forecasted total cost of completion (EACf) = Estimated total cost to complete
remaining work (ETC) + Cumulative actual cost of work completed (AC)
8
FA - Chapter 13
BUSI 2550
To Complete Performance Index (TCPI) – measures amount of value each remaining dollar in
budget must earn to stay on budget
o TCPI = (BAC – EV) / (BAC – AC)
Other Control Issues
11/12/2018
Issues in maintaining control of projects
o Technical performance measurement
o Scope creep
o Baseline changes
o Data acquisition costs and problems
9
Title: Chapter 13 Notes - Monitoring Progress
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550
Description: Chapter 13 Notes - Monitoring Progress Business and IT Project Management BUSI 2550